Dong Nai is one out of Vietnam "s leading prospects in terms of economic development, particularly for its industrial strength developed in the key economic region of the south. Most industrial estates were located to the south of Bien Hoa city spreading longwise National Highway 51 about 47 km to Go Dau. Tam Phuoc Industrial Park is situated within the industrial estates master planning of Dong Nai province. Together with An Phuoc 1 I.P., An Phuoc 2 I.P, they do form a relatively large industrial complex on National Highway 51. Tam Phuoc I.P. coupled with Tam Phuoc residential area, new city of Tam Phuoc, Long Thanh town becomes a source for labour force, services and industrial estate related development.
The project site has an area of 18 hectares located in the planned residential area for the purpose to support the industrial park development. There is already the detailed land use planning with approval, of which meaning is to support Tam Phuoc industrial park in providing housing to families whose houses are in the site clearance area for the industrial park construction, and to workers who are working in surrounding areas, and in creating favorable investment environment by providing land pool to high income workers and managing staff working in the industrial park.
Furthermore, the construction of Tam Phuoc residential area will contribute to the development of Tam Phuoc new city with sufficient conditions that a city must have, and then the infrastructure system will gradually be constructed for better standard of living.
(As a matter of size, those projects mentioned herein just provide general information regarding background and bases for the setup thereof. Other related contents, e.g. SWOT Analysis, Business Plan, Marketing Plan, Revenue Forecast, Financial Forecast, etc…are not available on this medium)
The project to develop 15ha Tam Phuoc resettlement area in Tam Phuoc commune, Long Thanh district, Dongnai province is for the following objectives:
● To construct a perfect infrastructure system synchronized with the project site.
● To satisfy actual needs of housing of experts and workers who live and work in Tam Phuoc industrial park.
● To perform the land use planning and to classify each planned area to be suited to the investment and business development trends in line with the development of the surrounding areas and of the whole newly established Tam Phuoc city.
To create beautiful landscape in the whole area.
The project site is on an area of 15 hectares in Tam Phuoc commune, Long Thanh district, Dongnai province:
● Bordering Tam Phuoc industrial park to the north.
● Bordering the existing residential area to the south.
● Bordering the planned residential area to the east.
● Bordering the Land Survey High School 3 to the west.
Master plan of the whole area
The 3-floor apartment building located to the east of the area, which is for workers to rent, is in the separate area between two internal roads and partly borders the industrial park. Such location of the building makes it isolated from others and suited to those who do shift work.
The villas for high-income workers and managing staff to lease are constructed to the north of the area. This position is 60m adjacent to the separate tree lines bordering the industrial park, which can help the air fresh and the villas separate from the others. The apartments to the west of the area are bordered by three sides of 20-m roads and the tree garden, and stay separate from the worker housing area.
The area for public utilities at the central part of the area, together with the tree gardens, creates a beautiful center of the whole area.
Land use structure
|
No. |
Land use classification |
Area (m 2 ) |
Rate (%) |
|
1 |
Land for housing ● Residential area ● Housing for workers and managing staff |
88.583 20.537 68.046 |
58,9 |
|
2 |
Area for traffic |
45.030 |
30.0 |
|
3 |
Area for tree planting |
11.076 |
7.4 |
|
4 |
Area for public utilities |
5.575 |
3.7 |
|
TOTAL |
150.264 |
100 |
|
Note : Tree planting area includes those concentrated for planting trees not those that are between apartment building blocks.
Allocation of Construction items
Housing:
This includes 832 houses, of which 160 are for resettled families, 588 for workers and 84 for high-income workers and managing staff.
Houses for resettled families: Including 160 houses, of which
|
|
|
Houses for workers: Including 588 ones, of which
Apartment building A
|
|
|
Total apartments 42/block x 10 blocks = 420 apartments (area for each apartment is from 58 m2/apartment to 64 m2/apartment)
Apartment building B
|
● Area for construction |
: 480 m2 |
|
● Floor area |
: 1.440 m2 |
|
● Building height |
: 3 floors |
Total apartments 13/block x 8 block = 104 apartments (area for each apartment is from 58 m2 to 64 m2)
Houses for high-income workers and managing staff: 84 apartments, of which
Villa: 24 villas
|
● Land area |
: from 340 m2 to 400 m2 |
|
● Area for construction |
: 146 m2 |
|
● Floor area |
: from 250 m2/apartment to 300 m2/apartment |
|
● Building height |
: 2 floors |
Apartment block D: including 60 apartments
|
● Area for construction |
: 854 m2 |
|
● Floor area |
: 3.389 m2 |
|
● Building height |
: 4 floors |
Total apartments 60 apartment /block (area for each apartment is 64 m2/apartment)
Area for public utilities:
The area for public utilities is at the central part of the project site, connecting with the tree gardens in order to perform its own functions:
● To provide bare necessities to nearby residents.
● To have canteens.
● To have retail outlets, public facilities such as hair cutting, health care services.
● To have meeting clubs for entertainment activities.
● To have sports area including swimming pool, tennis course with flower gardens and lawns
|
● Total area |
: 5.575 m2 |
|
● Area for construction |
: 800 m2 |
|
● Floor area |
: 1.128 m2 |
|
● Building height |
: 2 floors |
In summary, the project will make a certain contribution to enhance the beauty of the whole urban area and create more land pool to Dongnai province"s in particular and the whole country"s in general. The project master plan has also set out sufficient resolutions to limit bad effects to the environment. However, there must be specific regulations applied to all building executive bodies as well as regulations on management of the residential areas in order to minimize probable bad effects to the environment of the whole area.
(As a matter of size limit, those projects mentioned herein just provide general information on background of and bases for the setup thereof. Other related contents, e.g. SWOT Analysis, Business Plan, Marketing Plan, Revenue Forecast, Financial Forecast, etc…are not exhaustive).